Aug. 12 board minutes show a named vendor, cost and completion target for one piece of the Ballard Road campus project.

WSWHE BOCES’ Aug. 12 board minutes show the agency approved Comalli Group, Inc.’s security-platform installation at its new Wilton campus facility for an estimated $781,632.97, with completion by May 31, 2027 or sooner.

WSWHE BOCES has added a new documented cost item to its Wilton campus project.

According to the board’s Aug. 12, 2026 meeting minutes, the BOCES board approved Comalli Group, Inc.’s proposal for a security platform and installation at the new campus facility in Wilton. The minutes put the estimated project cost at $781,632.97 and set an overall completion date of May 31, 2027 or sooner.

That is a more specific public record than the broader groundbreaking announcement reported earlier this week. It adds a named contractor, a dollar amount and a deadline for one part of the buildout.

The next records to watch are the Sept. 9 BOCES board materials and any additional Vision 2027 contract approvals tied to the Ballard Road campus.