BridgeNY Heath Road over Sturdevant Creek BIN 3304520, PIN 1762.42

The County will design, let, and construct the project.

Record through Mar 18, 2026Coverage
Documented sequence

Development timeline

Financial record

Money and approvals

$360,000

Professional engineering services for the BridgeNY bridge replacement project on Heath Road over Sturdevant Creek.

Contract · linked public meeting

Approved
What happens next

Deadlines and follow-ups

Date not documented

Construction of the Heath Road over Sturdevant Creek project must begin no later than 24 months after award and be completed within 30 months.

Follow-up documented; date not established

Open